Skip to content
  • There are no suggestions because the search field is empty.

Activities Sitting on/Riding the Data Date

Activities Sitting on the Data Date:
 
What it is:These are activities that are scheduled to start exactly on the data date, based on the logic that was incorporated into the schedule.
 
Best Practice:Consider promoting visibility into activities with the 3-week and 6-week look ahead reports. Potentially, incorporate into the schedule quality profile to promote awareness among the teams.
 
 
 
Activities Riding the Data Date:
 
What it is:These are activities that are not driven by logic. They are being driven by the data date and will continue to be pushed week to week until actualized or re-sequenced. They are technically eligible to begin at the time of the update and often represent work that is ready to start or currently in progress.
 
Best Practice:Every activity should have detailed enough logic in order to avoid activities riding the data date. Highly recommend adding this metric to your quality profile and completing regular reviews and updating as needed.