Are there any best practices for using P6 schedules with SmartPM?

To ensure smooth integration:

  • Only export one project per XER file.
  • Verify that activity IDs and logic ties are complete.
  • Check that baseline and update data are consistent.
  • Avoid including unnecessary subprojects or templates.

Following these practices helps prevent errors and ensures accurate schedule analytics in SmartPM.