Are there any best practices for using P6 schedules with SmartPM?
To ensure smooth integration:
- Only export one project per XER file.
- Verify that activity IDs and logic ties are complete.
- Check that baseline and update data are consistent.
- Avoid including unnecessary subprojects or templates.
Following these practices helps prevent errors and ensures accurate schedule analytics in SmartPM.