CPM Key Terms
CPM scheduling uses a handful of core terms, such as activities, durations, logic ties, float, and the critical path, to explain how work connects and moves across a project. This section gives you the essentials so you can read and build a CPM schedule with confidence.
|
Term |
Definition |
|
Actual Start/Actual Finish |
The real dates when an activity began and ended, used to update schedule progress. |
|
Activity |
A task or piece of work in the schedule that consumes time and resources. |
|
Activity ID |
A unique identifier assigned to each task in the schedule. |
|
Activity Type |
Categorization of an activity, such as milestone, level of effort, or task. |
|
Baseline |
The approved version of the project schedule, used as a reference for tracking progress. |
|
Baseline Start/Finish |
Planned start and finish dates captured in the approved baseline schedule. |
|
Calendar |
Defines working and non-working time (holidays, weekends, shifts). |
|
Constraint |
A restriction placed on an activity’s start or finish (e.g., “Start No Earlier Than”). |
|
Critical Path |
The longest chain of dependent activities with zero float; determines the earliest project completion date. |
|
Crew Logic |
Sequencing activities based on available resources (e.g., one crew moves from task to task). |
|
Data Date |
The “status date” in a schedule; the point in time when progress is recorded and future work is forecasted. |
|
Actual Percent Complete |
How complete the project is according to the latest schedule update |
|
Finish-to-Finish |
A logic tie where one activity must finish before another can finish. |
|
Finish-to-Start |
A logic tie where one activity must finish before another can start. |
|
Total Float (Slack) |
The amount of time an activity can be delayed without affecting the project end date. |
|
Free Float (Slack) |
The amount of time an activity can be delayed without affecting its successor activities. |
|
Lag |
A duration added to a logic tie between two activities (e.g., drywall must cure for 2 days before painting starts). |
|
Logic |
The relationships between tasks that establish sequence and drive the critical path. |
|
Milestone |
A marker that represents a key event or deliverable. |
|
Near-Critical Path |
Activities with float values just above zero (often less than 10 days) that are high risk. |
|
Planned Percent Complete |
The percentage of work scheduled to be completed by a given date according to the baseline schedule. |
|
Schedule Performance Index |
A measure of schedule efficiency: Actual Percent Complete divided by Planned Percent Complete |
|
Schedule Quality |
A measure of the reliability of a schedule, based on best practices and quality checks. |
|
Start-to-Finish |
A logic tie where one activity cannot finish until another activity has started (least common relationship). |
|
Start-to-Start |
A logic tie where one activity cannot start until another activity has started. |
|
Work Breakdown Structure (WBS) |
A hierarchical framework in CPM construction that breaks a project into phases, deliverables, and activities to organize scope and guide scheduling. |