Importing a Baseline Schedule (Essentials )
Setting up your project in SmartPM starts with importing your baseline schedule.Whether you’re setting up a new project or adding additional milestones later, SmartPM makes it easy to ensure your schedule is ready for analysis and monitoring from day one.
Import your Baseline Schedule:
- Navigate to the Project List and click “+ Add Project”.
- Fill in the project details including
- Project Name: Something unique to that project
- Project Source: Choose the file type of the schedule set you will be importing. (Keep in mind all schedules imported into the project must be the same type)
- Country and Postal Code: Update the city and state to assist with geo-coding.
- Click Next
- If your organization has Metadata fields set up, you will be asked to assign them to the project you are creating, and click next.
- Under Upload Schedule, upload your baseline schedule by dragging and dropping or clicking on the upload button and navigating to the schedule
- Baseline schedules should be uploaded independently
- If necessary, enter a contractual end date and/or the hit rate goal
- Select activities to track.
- Click Next to continue.
- Once your schedule processes, click Next.