Decreased Percent Complete
Decreased Percent Complete refers to activities where the percent complete has decreased in a subsequent schedule update. Example: one activity was at 50% complete; after the most recent update, the activity is at 25% complete.
How decreased percent complete affects the schedule:
- Suggests reporting errors or misinterpretation of progress.
- Affects accuracy of project tracking.
- Can hide delays or misrepresent project health.
Best Practices:
- Ensure percent complete reflects actual progress.
- Investigate decreases to determine the cause.
- Document progress updates consistently.