Flagging Changes in SmartPM

Flagging changes lets you call attention to important updates in your project schedule, making it easier to track adjustments, discuss them with your team, or analyze their impact later. This feature ensures that critical shifts in timelines, dependencies, or task status don’t get overlooked and can be referenced whenever needed.

  1. Click the desired project from the Project List.
  2. From here, click Analysis from the top menu bar.
  3. Click Changes from the side menu bar.
  4. Locate the row with the scheduled date associated with the change you want to flag, then select the appropriate change type from the table.
  5. Click the Flag icon next to the changes you would like to flag. 
  6. Flagged changes will be accessible in the Flagged Changes column for that schedule date.