How do I fix my end date discrepancies?

SmartPM recommends the following actions:


  • Ensure all activities are properly linked with correct logic (FS, SS, FF, or SF).
  • Verify that the status date in MS Project matches the update you’re importing.
  • Avoid manually scheduled tasks or summary tasks that don’t have explicit logic.
  • Use Mark-On-Track to update actual progress accurately in MS Project before import.