How do status dates affect my schedule in SmartPM?

The status date in MS Project determines which activities are considered “actualized” versus “future.”

  • If the status date is incorrect, SmartPM may show activities as late or early incorrectly.
  • Always verify the status date before exporting MS Project files to SmartPM.