How do status dates affect my schedule in SmartPM?
The status date in MS Project determines which activities are considered “actualized” versus “future.”
- If the status date is incorrect, SmartPM may show activities as late or early incorrectly.
- Always verify the status date before exporting MS Project files to SmartPM.