Metrics Available in the Project List
| Actual Progress | The percentage of work completed as of the current data date, based on the most recent schedule. | How much of the project is truly done right now. |
| Average Duration Variance | The average difference in calendar days between planned activity durations and their actual durations for all activities. | On average, are tasks taking longer or shorter than planned. |
| Baseline Actual Progress | The percentage of work completed as of the data date in the baseline schedule. | How much work was done according to the original baseline tracking point. |
| Baseline Average Duration Variance | The average difference between planned activitiy durations and actual durations in the baseline schedule. | Whether baseline tasks took shorter or longer than first planned. |
| Baseline Contractual End Date | The contractual finish date recorded in the baseline schedule. | The agreed finish date when the project began |
| Baseline Contractual Float | The difference (in working time) between the baseline project finish date and the contractual completion date, representing the schedule contingency available at the baseline stage. | The schedule cushion in the baseline plan. |
| Baseline Cost: Actual Progress | The actual cost associated with progress achieved as of the baseline data date. | How much you'd spent by this point in the baseline. |
| Baseline Cost: Earned | The earned value cost based on work completed in the baseline schedule. | The value of work performed according to the baseline. |
| Baseline Cost: Performance Index | The cost performance index (earned / actual) from the baseline schedule. | How cost efficiency compared to plan in the baseline. |
| Baseline Cost: Planned | The total cost planned in the baseline schedule. | How much the baseline budgeted for the project. |
| Baseline Cost: Planned Progress | The cost assocaited with the progress planned by the baseline data date. | Planned spend by that point in the baseline. |
| Baseline Cost: Remaining | The cost left to complete according to the baseline schedule. | How much budget was left in the original plan. |
| Baseline Data Date | The "as of" date in the baseline schedule. | The date the baseline schedule data represents. |
| Baseline Duration | The total length of the project from start to finish in the baseline schedule. | How long the project was originally planned to take. |
| Baseline Earned Days | The number of workdays earned based on progress in the baseline schedule. | How many planned days were achieved in the baseline. |
| Baseline End Date | The date of the last activity in the primary scenario of the very first schedule in your project that you are measuring to. | The original completion date. |
| Baseline Predicted End Date | The projected finish date based on the baseline schedule's performance at that time. | What the finish date was expected to be when using baseline data. |
| Baseline Health | The overall risk score for the project in the baseline schedule. | Original health rating of the project at the start. |
| Baseline Manpower: Actual | The actual manpower recorded as of the baseline data date. | Workforce actually used in the baseline. |
| Baseline Manpower: Actual Progress | The manpower hours or headcount achieved as of the baseline data date compared to plan. | How manpower delivery compared to plan in the baseline. |
| Baseline Manpower: Earned | The manpower value earned based on work completed in the baseline schedule. | Labor achieved as planned in the baseline. |
| Baseline Manpower: Estimated | The manpower estimate in the baseline schedule. | How many workers/labor hours were planned initially. |
| Baseline Manpower: Performance Index | The manpower performance index (earned / actual) in the baseline. | How manpower efficiency compared to plan in the baseline. |
| Baseline Manpower: Planned | The planned manpower levels in the baseline schedule. | Labor headcount or hours originally planned. |
| Baseline Manpower: Planned Progress | The manpower planned to be achieved by the baseline data date. | Expected labor delivery at that point in the baseline. |
| Baseline Planned Progress | The percent complete planned by the baseline data date. | How far along the project should have been in the baseline. |
| Baseline Planned Recovery | Planned recovery effort in the baseline to address delays. | How the baseline intended to make up lost time. |
| Baseline Planned vs. Actual | Planned progress versus actual progress as shown in the baseline | If work was ahead or behind at the baseline date. |
| Baseline SPI | Schedule performance Index from the baseline schedule. | How work pace compared to plan in the baseline. |
| Baseline Schedule Quality | The schedule quality score for the baseline schedule. | How well the original schedule was built. |
| Baseline Source End Date | The end date from the first schedule file that became the baseline. | Where the original baseline finish date came from. |
| City | The city where the project is located | Helps identify the project's location for regional reporting |
| Compression | The effort per day now needed to finish on time compared to the baseline. Calculated only when multiple schedules are loaded and progress is between 1% and 90% | |
| Contractual End Date | The agreed project completion date in the contract | The official finish date you're obligated to meet. |
| Contractual End Date Variance | The difference in days between the current end date and the contractual completion date. | How far ahead or behind you are from the contract date. |
| Contractual Float | The total float between the current end date and the contractual completion date. | The schedule cushion you have before missing the contract date. |
| Cost: Actual Progress | The actual cost associated with the progress achieved as of the current data date. | How much you've actually spent based on completed work so far. |
| Cost: Earned | The earned value cost based on work completed to date. | The budgeted value of work performed so far. |
| Cost: Performance Index | A cost efficiency ratio calculated as earned cost / actual cost. | How efficiently you are spending compared to plan. |
| Cost: Planned | The total planned cost in the current schedule. | How much the project is currently budgeted to cost. |
| Cost: Planned Progress | The planned cost for the work expected to be complete by the current data date. | How much you planned to have spent by now. |
| Cost: Remaining | The cost left to complete the project based on the current schedule. | How much budget is still available for the rest of the work. |
| Country | The country where the project is located | Allows grouping and filtering by national location. |
| Critical Path Delay | The total days of delay on the critical path based only on actual progress to date. | How much progress delays have pushed the finish date. |
| Current End Date | The End Date from the latest schedule in the Primary Scenario. | |
| Data Date | The "as of" date for the current schedule data. | The date your schedule data is current to. |
| Duration | The total length of the project from start to finish, as defined in the current schedule. | How long the project is planned to take. |
| Duration Variance | The difference in days between the current project duration and the baseline project duration. | How much longer or shorter the project is now expected to be. |
| Earned Days | The number of workdays earned based on completed work to date, measured against planned productivity. | How many days of progress you've achieved so far. |
| End Date Variance | The difference in days between the current end date and the baseline end date. | How far off the project finish is from the original plan. |
| Health | Overall risk level for the end date of the project. | |
| Hit Rate | The percentage of activities that started and finished on time compared to the plan from the previous update. | How often planned activities happened as scheduled. |
| Manpower: Actual | The actual manpower recorded as of the current data date. | How many workers or labor hours have actually been used so far. |
| Manpower: Actual Progress | The manpower hours or headcount achieved as of the current data date compared to plan. | How manpower delivery is tracking against the plan |
| Manpower: Earned | The manpower value earned based on work completed to date. | The planned labor output for the work you've finished. |
| Manpower: Estimated | The current estimated manpower needed for the project. | The forecasted labor demand for the project. |
| Manpower: Performance Index | A manpower efficiency ratio calculated as earned manpower / actual manpower | How effieciently labor is being used compared to plan. |
| Manpower: Planned | The total planned manpower in the current schedule. | The number of workers or labor hours currently planned. |
| Manpower: Planned Progress | The manpower planned to be achieved by the current data date. | The labor output you expected to have by now. |
| Metadata fields | I.e., district manager, earned value, project type, region, revenue, scheduler, sector | |
| Milestone | A significant project event or target date tracked in the schedule. | A key checkpoint or goal within the project timeline. |
| Planned Progress | The percentage of work that was planned to be complete by the current data date, based on the latest schedule | Where you should be according to the plan. |
| Planned Recovery | The amount of work planned in the current schedule to regain lost time. | The effort built into the plan to catch up after delays. |
| Planned vs. Actual | Planned progress versus actual progress, compared to the baseline schedule. | |
| Postal Code | The postal or ZIP code for the project's location. | Useful for mapping and location-based searches. |
| Predicted End Date | The projected finish date based on current performance trends | When you're actually expected to finish. |
| Previous Actual Progress | The percentage of work completed as of the prior update's data date. | How much of the project was done at the last update. |
| Previous Average Duration Variance | The average difference between planned and actual activity durations in the prior update. | Whether tasks were running shorter or longer last period. |
| Previous Compression | The compression index from the prior update. | How hard you would have had to push to meet the date at the last update. |
| Previous Contractual End Date | The contractual completion date recorded in the prior update | The agreed finish date in the last period's schedule. |
| Previous Contractual End Date Variance | The difference in days between the prior update's end date and its contractual completion date. | How far ahead or behind the contract date you were last period. |
| Previous Contractual Float | The total float between the prior update's end date and contractual completion date. | The schedule cushion you had last period. |
| Previous Cost: Earned | The earned value cost from the prior update. | The budgeted value of work performed by the last update. |
| Previous Cost: Performance Index | The cost efficiency ratio (earned / actual) from the prior update. | How efficiently you were spending last period. |
| Previous Cost: Planned | The total planned cost from the prior update. | How much the project was budgeted to cost in the last update. |
| Previous Cost: Planned Progress | The planned cost for the work expected to be complete by the prior update's data date. | How much you planned to have spent by that point in the last update. |
| Previoius Cost: Remaining | The cost left to complete according to the prior update. | How much budget was still available last period. |
| Previous Critical Path Delay | The total days of delay on the critical path from the prior update. | How much progress delays had pushed the finish date at that time. |
| Previous Data Date | The "as of" date for the prior update's schedule data. | The date the last update's schedule was current to. |
| Previous Duration | The total project length in the prior update's schedule. | How long the project was planned to take last period. |
| Previous Duration Variance | The difference in days between the prior update's duration and the baseline duration. | How much longer or shorter the project was expected to be in the last update. |
| Previous Earned Days | The number of workdays earned based on progress in the prior update. | How many planned days of progress had been achieved last period. |
| Previous End Date | The project finish date in the prior update. | The planned completion date in the last update. |
| Previous End Date Variance | The difference in days between the prior update's end date and the baseline end date. | How far off the finish was from the original plan last period. |
| Previous Health | The overall risk score for the project in the prior update. | The health rating of the project at last update. |
| Previous Hit Rate | The percentage of activities that started and finished on time according to the prior update's plan. | How often planned activities happened as scheduled last period. |
| Previous Manpower: Actual | The actual manpower recorded as of the prior update's data date. | How many workers or labor hours were actually used last period. |
| Previous Manpower: Actual Progress | The manpower hours or headcount achieved by the prior update compared to plan. | How manpower delivery was tracking against plan last period. |
| Previous Manpower: Earned | The manpower value earned based on work completed in the prior update. | The planned labor output for the work finished last period. |
| Previous Manpower: Estimated | The manpower estimate in the prior update's schedule. | The forecasted labor demand last period. |
| Previous Manpower: Performance Index | The manpower efficiency ratio (earned / actual) from teh prior update. | How efficiencly labor was being used last period |
| Previous Manpower: Planned | The total planned manpower in the prior update's schedule. | The number of workers or labor hours planned last period. |
| Previous Manpower: Planned Progress | The manpower planned to be achieved by the prior update's data date. | The labor output expected by that point last period. |
| Previous Planned Progress | The percent complete planned by the prior update's data date. | Where the project should have been last period. |
| Previous Planned Recovery | The recovery effort planned in the prior update to address delays. | How you intended to make up lost time last period. |
| Previous Planned vs. Actual | Planned progress versus actual progress shown in the prior update. | If work was ahead or behind at the last period. |
| Previous Predicted End Date | The projected finish date based on the prior update's performance trends. | When you were expected to finish last period. |
| Previous SPI | The schedule performance index from the prior update. | How your work pace compared to plan last period. |
| Previous Schedule Quality | The schedule quality score for the prior update. | How well the schedule was built in the last update. |
| Previous Source End Date | The end date from the schedule file in the prior update. | The finish date from the last uploaded schedule file. |
| Schedule Quality | A score showing how well the schedule is built, based on industry best practices. | |
| Source End Date | The end date from the original uploaded schedule file. | The finish date from the schedule you first imported. |
| SPI | The rate of actuall progress compared to planned progress. SPI = Actual % / Planned % | |
| Start Date | The planned start date of the project in the current schedule. | When the project is scheduled to begin. |
| Start Date Variance | The difference in days between the current start date and the baseline start date. | How much the project start date has shifted. |
| State | The state, province, or region where the project is located. | Enables filtering and analysis by sub-national region. |