Metrics Available in the Project List (Essentials)
| Actual Progress | The percentage of work completed as of the current data date, based on the most recent schedule. | How much of the project is truly done right now. |
| Baseline Actual Progress | The percentage of work completed as of the data date in the baseline schedule. | How much work was done according to the original baseline tracking point. |
| Baseline Data Date | The "as of" date in the baseline schedule. | The date the baseline schedule data represents. |
| Baseline Predicted End Date | The projected finish date based on the baseline schedule's performance at that time. | What the finish date was expected to be when using baseline data. |
| Baseline Health | The overall risk score for the project in the baseline schedule. | Original health rating of the project at the start. |
| Baseline SPI | Schedule performance Index from the baseline schedule. | How work pace compared to plan in the baseline. |
| Baseline Schedule Quality | The schedule quality score for the baseline schedule. | How well the original schedule was built. |
| Baseline Source End Date | The end date from the first schedule file that became the baseline. | Where the original baseline finish date came from. |
| City | The city where the project is located | Helps identify the project's location for regional reporting |
| Compression | The effort per day now needed to finish on time compared to the baseline. Calculated only when multiple schedules are loaded and progress is between 1% and 90% | |
| Country | The country where the project is located | Allows grouping and filtering by national location. |
| Critical Path Delay | The total days of delay on the critical path based only on actual progress to date. | How much progress delays have pushed the finish date. |
| Current End Date | The End Date from the latest schedule in the Primary Scenario. | |
| Data Date | The "as of" date for the current schedule data. | The date your schedule data is current to. |
| End Date Variance | The difference in days between the current end date and the baseline end date. | How far off the project finish is from the original plan. |
| Health | Overall risk level for the end date of the project. | |
| Hit Rate | The percentage of activities that started and finished on time compared to the plan from the previous update. | How often planned activities happened as scheduled. |
| Metadata fields | I.e., district manager, earned value, project type, region, revenue, scheduler, sector | |
| Milestone | A significant project event or target date tracked in the schedule. | A key checkpoint or goal within the project timeline. |
| Postal Code | The postal or ZIP code for the project's location. | Useful for mapping and location-based searches. |
| Predicted End Date | The projected finish date based on current performance trends | When you're actually expected to finish. |
| Previous Actual Progress | The percentage of work completed as of the prior update's data date. | How much of the project was done at the last update. |
| Previous Compression | The compression index from the prior update. | How hard you would have had to push to meet the date at the last update. |
| Previous Critical Path Delay | The total days of delay on the critical path from the prior update. | How much progress delays had pushed the finish date at that time. |
| Previous Data Date | The "as of" date for the prior update's schedule data. | The date the last update's schedule was current to. |
| Previous End Date | The project finish date in the prior update. | The planned completion date in the last update. |
| Previous End Date Variance | The difference in days between the prior update's end date and the baseline end date. | How far off the finish was from the original plan last period. |
| Previous Health | The overall risk score for the project in the prior update. | The health rating of the project at last update. |
| Previous Hit Rate | The percentage of activities that started and finished on time according to the prior update's plan. | How often planned activities happened as scheduled last period. |
| Previous Predicted End Date | The projected finish date based on the prior update's performance trends. | When you were expected to finish last period. |
| Previous SPI | The schedule performance index from the prior update. | How your work pace compared to plan last period. |
| Previous Schedule Quality | The schedule quality score for the prior update. | How well the schedule was built in the last update. |
| Previous Source End Date | The end date from the schedule file in the prior update. | The finish date from the last uploaded schedule file. |
| Schedule Quality | A score showing how well the schedule is built, based on industry best practices. | |
| Source End Date | The end date from the original uploaded schedule file. | The finish date from the schedule you first imported. |
| SPI | The rate of actuall progress compared to planned progress. SPI = Actual % / Planned % | |
| Start Date | The planned start date of the project in the current schedule. | When the project is scheduled to begin. |
| State | The state, province, or region where the project is located. | Enables filtering and analysis by sub-national region. |