Release 6.16 - September 15, 2023
- Should Have Started / Should Have Finished Report
- Add the ability to quickly filter by the donut chart slices
- Add a Global Configuration to allow for slippage when determining whether activities are late
- Add baseline information to Velocity Report
- Add Executive Dashboard PDF report
- Add a Global Configuration to lock in the end dates as presented in the baseline schedule for analysis
- File Importing
- Fix an issue causing MPP imports to fail due to Elapsed Durations
- Add specific circular reference error for MPP imports
- Update the PPX import process for partial second date formats
- Fix where SmartPM would read Friday and Saturday as weekends in some XML files
- Skip the Track to Activities step in Project Create for Project Plans that do not include Activity Tracking
- Fix an issue causing the Trend Graphs to scale incorrectly
- Fix where users could not remove Metadata Filters on the Company Dashboard
- Adjust the actual percent complete calculation to better account for activities with an actual start date with the same timestamp of a schedule update