Add Global Configuration "Point of Slippage Calculation"
Changes when "Point of Slippage Calculation" is set to Contractual
The Company Dashboard displays "Contractual Days Late" in place of scheduled "Days Late"
The Company Dashboard displays "Contractual End Date" in place of "Baseline End Date"
The Company Dashboard displays "Scheduled End Date" in place of "Current End Date"
Additional Contractual End Date and Milestone Float information is added to the "Current End Date" section of the Narrative Report
Add the Milestone Float column to the Delay Table and Summary Trends Table
Custom Reporting - ALPHA Phase
Add the ability to create a limited Custom Report at the Project level for Schedule Admins.
Add Excel Export for the Executive Dashboard "Projects" Card
Better handle situations where the Remaining Duration on an already started activity is increased
Add cross-tab session refreshing.
Collapse dropdown menus when clicking anywhere off of them
Add Project, Model, and Milestone names to Subscription email subject lines
Ensure the Late and Early Date Progress Curves diverge starting at the baseline schedule.
Fix a rounding issue causing the number of Critical Path Activities identified by Schedule Quality to be different than what is shown in the Gantt Chart.
Fix an issue causing SmartPM to misidentify activities as Out-of-Sequence.
Fix an issue causing the Executive Dashboard Initial Set Up modal to reload
Fix where the Data Date on the Trends Graphs generated by a Subscription contained incorrect formatting.
Update the Change Log to ignore Constraint Changes when they occur due to Microsoft Project's scheduling processing.
Fix an issue with manually setting the Data Date on import for Microsoft Project
Limit float values to two decimal places in the UI
Fix an display issue causing LOE exclusion in the Schedule Quality Editor to show as Milestone exclusion.
Fix an issue causing circular logic when running Advanced Models with Revert and Reject