Release 9.43 November 2nd 2026

New Features

  • Quality Profile Configuration: Quality profiles now give you more control over how key metrics are calculated:
    • Relationship Counts: Every relationship metric now includes an option to count relationships where the predecessor or successor is complete or filtered out. Previously, these relationships were always excluded from the count.
    • Constraint Counts: “As Late As Possible” activities can now be included in the constraint count. “As Early As Possible” remains excluded, since it’s the default for every unconstrained activity.
    • High Duration Activities: You can now choose whether activities are flagged based on remaining duration or planned duration.
  • Dashboard Project Status Filter: A new filter on the Dashboard lets you view Completed or Active projects, making it easier to focus on the work that matters to you right now.

Bug Fixes

  • Quality Filters: Fixed an issue where some filters were missing from the Negative Lag metric and other quality metrics. All filters are now available as expected. 
  • Reports: Fixed an issue that prevented adding two Project Cards per page.
  • Powerproject Import: Fixed an issue that caused some Powerproject schedules to fail during import.
  • Project Import: Files with a missing WBS no longer fail silently; a clear error message is now displayed.
  • Modeling: Fixed an issue where Revert and Reject rules failed when Resume By dates were present.
  • Add Users in Bulk: Fixed an issue where the upload failed if the file included someone who was already a user in the company.
  • Billing & Subscription: Fixed a layout issue where the page content extended beyond the screen.
  • Should Start/Finish Report: Fixed an issue where some dates were displayed incorrectly.
  • Schedule Range Override: The override now uses data from the selected schedule file instead of the latest file.