Schedule Performance Index
Schedule Performance Index (SPI) is a measure of how efficiently your project is progressing relative to the baseline schedule.
The formula to calculate SPI is: Actual Progress / Planned Progress.
SPI helps you to see if you’re shear, on track, or behind schedule.
- SPI = 1.0: You are exactly on schedule
- SPI< 1.0: You are behind schedule
- SPI > 1.0: You are ahead of schedule.
Actual Progress: How much progress your current schedule is reporting
Planned Progress): How much progress your baseline schedule prescribed by the date of the data date of your current schedule
Example:
Actual Progress = 60%
Planned Progress= 75%
Actual Progress (60) / Planned Progress(75) = .80
In the above example, the project is running at 80% efficiency relative to the plan, meaning the project is behind overall.