Schedule Updating Best Practices
Updating is more than just entering actual start and finish dates. It’s about preserving schedule logic and ensuring the CPM remains a trustworthy forecasting tool.
When updating, focus on:
- Critical and Near-Critical Paths: Always review how updates impact these paths. Delays here often dictate overall project completion.
- Logic Ties: Verify that relationships between activities are still valid and adjust if site conditions or plans change.
- Durations and Remaining Work: Update remaining durations based on actual performance, not just original estimates.
- Data Date: Move the data date forward consistently (usually monthly, or more often for fast-moving projects). This ensures progress is measured against a realistic timeline.
Steps to Schedule Updating:
Step 1: Walk the Site and Status the Job
- Physically walk the project site to see actual progress.
- Talk to field supervisors, subcontractors, and crews to confirm progress and verify what’s really happening
- Confirm which activities have started, are in progress, or are completed.
- Note delays, obstacles, or resource constraints directly from the field.
- Use this field intel to ground your updates in reality.
Step 2: Update the Schedule with Site Walk Info
- Enter actual start and finish dates for activities.
- Update percentage complete for ongoing tasks.
- Adjust durations if work is progressing faster or slower than planned.
- Ensure float values and the critical path are recalculated after updates.
Step 3: Identify and Incorporate Necessary Changes
- Add scope changes, resequenced work, or newly identified dependencies.
- Document reasons for schedule changes to maintain transparency.
- Reassess the critical and near-critical paths to anticipate potential delays.
- Communicate changes with the project team and owner for alignment.