The SmartPM Report
The SmartPM Report is a concise, executive-level summary that provides critical schedule information to facilitate discussions with stakeholders. It's designed to be used in meetings, audits, or any situation where a clear, high-level overview of project performance is needed.
Key Components include:
- Schedule Quality Issues: identifies any schedule quality problems that may pose risks to the project’s success
- Summary Progress Graphic: Visual representation of your schedule, summarized by WBS or Activity Codes, and featuring historical critical paths
- Delay Table: Details of any delays, including their causes and impacts on the project timeline.
- Audit Log Changes: A record of all critical changes made to the project schedule, ensuring transparency and accountability.
To access the report:
- Navigate to your project from the Project List.
- Click Reporting from the top navigation bar.
- Click the ‘play’ icon next to the SmartPM report.
- Select the schedule update you want to base the report on.
- Choose the range of WBS Levels for the summary bars in the graphic.
- The maximum selectable range is one level apart.
- Click “print” to generate the report.