Actual Dates After the Data Date (e.g. Future Actual Dates)
Upon importing
- If an activity has a future Actual Start Date without an Actual Finish Date, SmartPM sets the activity to not started.
- If an activity has a future Actual Start Date with an Actual Finish Date, SmartPM accepts the dates.
- SmartPM accepts all Actual Finish Dates