Adjusting Activity Attributes

Users can adjust Activity Attributes via the One-Off Change Scenario Condition

- Go to the Conditions Tool

-Click the One-Off Change option 

-Select the schedule  

-Then in the Gantt view, select the activity you would like to Edit

-Once the activity is selected > click "Edit Attributes"

-Edit any attributes you would like > Click "Save"

-Once you are done editing your activity attributes > Click the  Save One-Off Change Rule option > Name the One-Off Change > Click "Save"

 

-To create the model based on this scenario that was created you will navigate back to the Project Workspace screen and select the "Advanced Model" option

-Select the schedules you want to include in the model

-Select the Scenario you had just created to apply to the model and click "Save"

-The model will then be created