- How SmartPM Handles Schedules with Data Integrity Issues
- Schedules with Data Integrity Issues
% Complete
- If the % Complete rolls backward (e.g. from 50% to 20%), SmartPM ignores the roll back and keeps the previously reported % Complete.
- If an activity with less than 100% complete is given an Actual Finish Date, SmartPM adjusts the % complete to 100%.