Current End Date
The Current End Date is the end date of the most recent updated schedule.
Key Definitions:
- Current Finish Date, a.k.a Current End Date: "This date is based on the latest projected date. If all Activities have been completed, it will be based on the last actual date".
- Current Duration: "Current Start Date - Current Finish Date".