Dangling Activities

These are activities that are unbounded, missing a FS/SS predecessor and/or FS/FF successor. Having dangling activities in a CPM schedule can lead to scheduling inaccuracies, misrepresentation of task relationships, and increased project risk. It is essential to ensure that all activities have well-defined logical dependencies to maintain a clear, accurate, and comprehensive project schedule that accurately reflects the real-world relationships between tasks.


  • Lack of Logical Dependency: Dangling activities are tasks that do not have well-defined predecessors or successors. In a CPM schedule, the proper definition of logical dependencies between activities is crucial for ensuring that the project schedule accurately reflects how work should be executed. Dangling activities break this logical chain and may lead to confusion about task relationships.
  • Misrepresentation of Project Reality: Dangling activities do not accurately represent the real-world relationships between tasks. They may create the impression that certain activities can be executed independently or that there are missing dependencies that could lead to project disruptions. This misrepresentation can lead to scheduling inaccuracies and unrealistic expectations.
  • Risk of Overlooking Tasks: Dangling activities may be overlooked or forgotten in the planning and execution phases of a project. This can result in incomplete work or the omission of crucial tasks, leading to project delays and a potential negative impact on project quality.
  • Reduced Accountability: When activities lack clear predecessors or successors, it can be challenging to establish accountability for task completion or coordinate the sequence of work. Team members may not clearly understand their responsibilities or the order in which tasks should be executed, which can lead to a lack of accountability.
  • Impaired Critical Path Analysis: Dangling activities can interfere with the accurate identification of the critical path, which is a sequence of activities that determines the project's overall duration. If the dependencies are not clearly defined, it can be difficult to determine which activities are most critical to the project's success.
  • Risk of Incomplete Work: Dangling activities may result in incomplete work if they are not accounted for or managed properly. This can lead to rework, additional costs, and project delays as tasks are retroactively added to the schedule.