Flagging Changes

This video shows you how to identify changes that you want to flag for discussions you will have later.

Navigate to the Trends Graphs to select the update periods you want to flag:

  1. Click on the name of a project to get to the Project Dashboard
  2. Select the radio button to the left of “Full Schedule”. You can only flag changes through the original scenario because the original scenario is going to have the base set of changes. Changes may fluctuate from scenario to scenario. 
  3. Click on the “Trends” graph icon on the right hand menu bar and you will see a summary.
  4. Click on the word “Graphs” to see the Trends graphs and Scroll to the third graph, “Schedule Changes Over Time” a graph that shows the changes that have occurred from update to update. You will see the places where the largest number of changes occurred in the schedule. 
  5. Compare the periods with the largest number of changes with the Schedule Delay Over Time graph to see the correlation between the changes and acceleration being experienced in the project. Acceleration is shown in green on the “Delay Over Time” graph. 
  6. Determine which updates you want to focus on. Usually you will select the updates with the most changes.

 

Flag the changes in the update periods you want to discuss in your next scheduling  meeting

  1. From the Project Workspace, select the radio button to the left of the Originals Key Milestone.
  2. Click on the “Changes” double arrow icon on the right hand menu bar.
  3. Click on the number value of one of the changes that you want to focus on. You will see a listing of all of the changes in the category you selected in that update period.
  4. Click on the “Change Item” header to sort the changes alphabetically
  5. Click on the flag icon to the left of the change items you want to flag and discuss in your next meeting. 
  6. If you want to discuss all of the changes, you can select all of the flags by clicking the “Toggle All Flags” button in the upper left corner of the screen. This will flag all of the changes in the update.
  7. Click the “X” in the upper right corner to exit the Changes list