Forecasted/Predicted Completion Date
How is Forecasted/Predicted Completion Date calculated?
SmartPM’s Forecasted Completion date uses a proprietary algorithm utilizing current progress to give a realistic estimate of what the completion date of the schedule should be, if you continue to work at your current SPI rate.
Note: Forecast Completion date will not populate until the project is approximately 50% complete.