Cost Metrics
Earned Cost – This Metric shows how much of the Activity’s Planned Budget should have been expended based on the Current Percent Complete.
- The Calculation is the Activity’s Planned Budget multiplied by the Activity’s Percent Complete
Planned Remaining Budget - This Metric shows how much of the Activity’s Planned Budget should be remaining based on the Current Percent Complete.
- The Calculation is the Activity’s Planned Budget minus the Activity’s Earned Cost