Trends: Schedule Delay Over Time
This video covers schedule delay graphic showing critical path delay, planed impacts, and overall end date variance. This graphic is found in the Trends group.
Schedule Delay Trend: Take a look at this nifty graph to see your Critical Path Delay, Future Recovery, and End Date Variance over time. If delays are mounting but end dates aren't changing, you'll see your future recovery (e.g. adjustments to future activity logic, sequencing, and duration) start to offset the delays. This video covers schedule delay graphic showing critical path delay, planned impacts, and overall end date variance. This graphic is found in the Trends group.