Skip to content
English
  • There are no suggestions because the search field is empty.

Viewing/Adding/Editing/Deleting Logical Relationships in the Project

Logic is a term used to describe a dependency between a Predecessor Activity and a Successor Activity, where the Predecessor Activity determines when its Successor Activity can start or finish. The Scheduling Engine takes into account all assigned Logic ties to determine the planned dates for performing Project Activities.

 

-Users can adjust Logic Ties via the One-Off Change Scenario Condition

-Through the One-Off Change process, select the Activity for which you would like to adjust the logic. 

-Select the schedule

-You will be brought to the Gantt chart view, where you can search/select an activity to view/add/edit/delete the activity's logical relationships

-Click the circle icon next to the  intended activity

  • To add a Predecessor Activity, click the  'Add Predecessor' button next to the Predecessors table
  • To add a Successor Activity, click the 'Add Successor ' button next to the Successors table

-Click the Activity drop-down menu to select the Activity to be Logically Tied to the initially selected Activity

  • Developer's Tip: Quickly filter for the Activity by utilizing the Search field in the drop-down menu

-

-Click the Dependency Type drop-down menu to select the type of Logic Tie to be assigned

  • Developer's Tip: There are 4 types of Logic ties available:
    • Finish to Start – The Predecessor Activity must be finished before the Successor Activity is started
    • Start to Start – The Successor Activity can start once the Predecessor Activity has started
    • Finish to Finish – The Successor Activity can finish once the Predecessor Activity has finished
    • Start to Finish – The Successor Activity can finish once the Predecessor Activity has started

--

-Enter the amount of Lag to be used in the Logic Tie in the Dependency Lag field

  • Lag is a modification of the Logic Tie that creates a delay in the successor activity. For example, in a finish-to-start dependency with a two-day lag, the successor activity cannot start until two working days after the predecessor activity has finished

Click -Click the blue check mark to Save

 

 Sometimes Logic Ties need adjusting. Here is how to Edit them:

From the Logic window, select the Logic Tie to be edited

Click the Blue Pencil to initiate Edit mode

Make edits and click the Blue Check Mark to Save

Other times, Logic Ties need to be removed completely. To Delete a Logic Tie, you should:

From the Logic window, select the Logic Tie to be deleted

Click the Red Trash Can

Once complete making changes, click  'Save One-Off Change Rule', Name & Save.

 

Once saved, you will be able to create an advance model where you can apply this One-off change condition that was created