Schedule Quality: Total Relationships
This video covers total relationships, a ratio of total relationships to total activities.
Learn where to find the total relationships ratio derived from the schedule, why you want to see between 1.5:1 and 2:1, how this double checks crew logic, and why this is important to understanding the reliability of your schedule.