Below is a detailed list of customizable settings in SmartPM to optimize project management and reporting:
-
Activities Started With No Progress
Configure how activities with an actual start date but 0% completion are handled:-
Treat as Started: Assigns 1% completion to enable delay analysis.
-
Treat as Unstarted: Marks the activity as not started.
-
-
Calendars
Choose the calendar source for scheduling:-
Window Calendars: Use calendars from the current project window.
-
Last Update Calendars: Use calendars from the most recent update.
-
-
Ignore or Update Actual Start/Finish Dates
Decide how to handle changes to actual start/finish dates in later updates:-
Ignore Changes: Retain original actual dates.
-
Update Actuals: Reflect updated start/finish dates.
-
-
Analyzed Baseline End Dates
Control the end date displayed on the dashboard:-
Source File End Date: Shows the end date from the source file.
-
SmartPM Calculated End Date: Uses SmartPM’s calculated end date.
Note: Gantt chart dates always reflect SmartPM calculations. For discrepancies, refer to the "End Date Discrepancies" documentation.
-
-
Import or Ignore Level of Effort (LOE) Activities
Choose whether to include or exclude Level of Effort activities during import:-
Import LOE Activities: Include in project analysis.
-
Ignore LOE Activities: Exclude from analysis.
-
-
Set Actual Finish Date When Activity is 100% Complete
Configure how SmartPM handles activities that reach 100% completion but lack an end date:-
Set to File’s Data Date: Automatically assigns the file’s data date as the activity’s end date.
-
Leave Blank: Keeps the end date field empty.
-
-
Schedule Update Interval
Set the frequency for update alerts:-
Options range from daily, weekly, bi-weekly, or monthly intervals.
-
When overdue, the project’s data date turns red on the company dashboard.
-
-
Predicted Completion Date Display
Customize how the forecasted completion date is presented:-
Exact Date: Displays a specific predicted date.
-
Date Range: Shows a range within which the completion is expected.
-
-
Show Source End Date on Company Dashboard
Toggle visibility of the source file’s end date on the company dashboard:-
Show: Displays the source end date.
-
Hide: Omits the source end date.
-
-
Compression Calculation Based on Percent Complete
Define when to start and stop compression calculations:-
Start: Specify the % completion to begin compression tracking.
-
Stop: Specify the % completion to end compression tracking.
-
-
Schedule Quality Display
Configure how the quality metric appears on the dashboard:-
Selected Model and Milestone: Based on user-selected model and milestone.
-
All Schedules Model (Full Schedule Milestone): Uses all schedules with the full schedule milestone.
-
Selected Model (Full Schedule Milestone): Uses the selected model with the full schedule milestone.
-
-
Schedule Performance Index (SPI) Calculation
Determine the starting point for SPI calculation:-
Baseline Schedule Status: Starts from the baseline’s completion percentage (e.g., ignores initial 15% if already complete).
-
0% Completion: Calculates SPI from the project’s start.
-
-
Slippage Allowance for Late Activities
Set a buffer before an activity is marked as late:-
Days of Clearance: Choose 0–14 days.
-
Same Week Rule: Activities starting/ending in the same week as scheduled are not considered late.
-
-
End Date Tracking Method
Choose how the project end date is calculated:-
Full Float Path: Uses the latest activity in the path, even if it extends beyond the milestone.
-
Milestone Path: Reflects the milestone’s end date, ignoring later activities.
-
-
Point of Slippage Calculation
Define the reference for calculating project delays:-
Contractual End Date: Uses a user-defined date.
-
Scheduled End Date: Uses the baseline schedule’s end date (full schedule or milestone).
-
-
Log Calendar Worktime Changes
Decide whether to track changes to calendar worktimes:-
Log Changes: Record changes in the project’s change log.
-
Do Not Log: Exclude changes from the log.
-
-
Should Have Started/Finished Float Column
Configure float display in the Should Start/Should Finish report:-
Native Float: Shows negative float from the source schedule.
-
SmartPM Float: Uses SmartPM’s calculated float (no negative float, as days late are already tracked).
-
-
Near Critical Threshold
Set the float threshold for activities to be considered near critical:-
Enter a numerical value (e.g., 5) to define the maximum float days.
-
Input only numbers, without “days” or other text.
-
-
Allow Users to Bypass SmartPM Best Practices on Schedule Import
Control whether users can bypass SmartPM’s best practices (e.g., restrictions on very long activity durations or lags) during project import:-
No Bypass Allowed: Enforces all best practices for all users.
-
Allow Company Admins to Bypass: Permits users with company admin roles to bypass certain best practices by unchecking a box during import.
Note: Critical best practices, such as preventing circular references, are always enforced.
-
-
Foreman AI Chat Access
Enable or disable access to Foreman AI Chat for users:-
Enable: Allows users to access Foreman AI Chat.
-
Disable: Restricts access to Foreman AI Chat.
-
-
Automatically Update Contractual End Dates
Decide how SmartPM handles updates to contractual end dates for projects or milestones:-
Automatic Update: Automatically updates the contractual end date when changes are detected in the source file.
-
Manual Update: Retains the original contractual end date unless manually updated by the user.
-