Test Workweek - Advanced Modeling

Test Workweek

The Test Workweek model option allows you to see how the project would be impacted if you added extra day(s) to the workweek, or removed day(s) from the workweek in one step.

How to Create a Test Workweek Model:

  1. Click on the project name from the Company Dashboard to get to the Project Workspace.
  2. Click on “Test Workweek” under the Modeling menu on the left side.
    1. Select Activities: You will first choose what to Update Workweek On, such as: WBS, Activity Codes, or specific Activities.

    2. Name & Calendar: You can type the name of your model in the "Model Name" box. Then you will choose which Calendar Type that the model will be utilizing. The calendars for the project can be found in the Settings > Calendar tool in SmartPM.


    3. Click 'Save' and await model creation/completion from the Notifications tool. Once completed, you can click on the scenario model in the Model box on the upper right and select the new model you created.