Trends: High Total Float Percentage Over Time
High Total Float Trend: Minimizing high float allows the schedule to be reactive. Schedules with many activities with high float can be indicative of flawed logic and have a risk of inefficiencies resulting in an erroneous critical path. This video covers High Total Float Activity Percentage Over Time. This graphic is found in the Trends group.