Trends: Schedule Changes Over Time
Schedule Changes Trend: Changes happen! No schedule is the same at the end as when it began. Use this graph to track all the different types of changes over time along with the number of total activities. Identify periods of significant change or large increases in activities and consider whether or not a re-baseline is warranted. This video covers changes and what they affected over the course of the project in graphic form. This graphic is found in the Trends group.